Party wall basics for Medway houses

If your house shares a wall with next door, or you plan to dig close to their foundations, the Party Wall etc. Act 1996 probably applies. It is more manageable than it sounds if you start early.

When the Act applies

The Act covers work to a wall shared with a neighbour, building a new wall on the boundary line, and some excavation close to a neighbouring building. Typical Chatham triggers are a loft conversion that puts steel beams into the shared wall, a rear extension built up to the boundary, and cutting a chimney breast out of a party wall. Work that does not touch the shared wall or go near their foundations is usually outside it.

Notice comes first

You must serve written notice on the neighbour before the work starts. The length of notice depends on the type of work, and ranges from one to two months. Check the government's party wall guidance for the exact periods that apply to your project, and do not rely on a verbal chat over the fence. A notice is valid for a limited time, so do not serve it too far ahead of the start date.

What the neighbour can do

The neighbour can consent in writing, or they can dissent. If they do not respond within 14 days, a dispute is treated as having arisen. When there is a dispute, a surveyor is appointed, either one agreed by both of you or one each, and they produce a party wall award that sets out how and when the work is done. Being asked to consent is not the same as being asked to approve the design, so a neighbour cannot simply stop reasonable work.

Costs and records

As a general rule the person doing the work pays the reasonable surveyor costs, though who pays what can vary with the circumstances. It is common to have a schedule of condition recorded before work, with photographs of the neighbour's side, so any later cracks can be compared fairly.

It is separate from planning and Building Regulations

A party wall award does not give planning permission or Building Regulations approval, and those do not replace it. Treat all three as separate boxes to tick. In the older streets near the centre of Chatham, where terraces are narrow, a party wall issue is likely on almost any rear project, so we raise it at the first visit.

Be neighbourly

Tell your neighbour what is planned before the formal letter arrives. A friendly explanation of the dates, the noise and the contact person goes a long way to keeping the process simple.

Excavation near neighbouring buildings

The Act also covers digging close to a neighbour's building, which matters for extension foundations. In broad terms, notice can be needed where you dig within a few metres of a neighbouring structure and deeper than its foundations, with the distance depending on the depth involved. The exact tests are set out in the government's guidance, so check them against your plans rather than relying on a rule of thumb.

Boundary walls and fences

A garden wall that sits on the boundary line can also be a party wall, and different rules apply to a simple fence. If you plan to raise or rebuild a boundary wall, or build a new wall up to the line, ask before starting. It is a common source of disputes between neighbours.

Timing your project

Notices, surveyor appointments and an award all take time, so build them into the programme. If you leave them until the builders are due to start, the project can stall. It is sensible to serve notice as soon as drawings are settled, and well before the date you want work to begin.

If you are the neighbour

If you receive a notice, read it carefully and do not ignore it. You can consent, or you can ask for a surveyor to be appointed. Ask to see the drawings, and for a record of the condition of your side. Reply within the time allowed.

Where to find the official guidance

The government publishes an explanatory booklet on the Party Wall etc. Act 1996 that sets out the notice types, the periods and the model letters. It is written for householders and is worth reading before you serve anything. It is the best place to check the exact rules for your project.

Related pages

See full extensions, the notes for Chatham centre and the guide to how long a house extension takes.

Free site visit and quote

Tell us about the project at hello@chathambuilders.co.uk or on WhatsApp. We'll arrange a site visit to give you a proper quote.

More guides

Got a project in mind? We will come and look.

A free site visit and a written quote. Tell us what you are thinking, send photos if you have them, and we will find a time that suits.